Given Numbers: 589, 362, 554, 371, 442
955, 425, 233, 214, 143
Middle number = 233
Last digit of 233 = 3
A's 1 day work: \( \frac{1}{10} \)
B's 1 day work: \( \frac{1}{20} \)
Step 1: A and B work for 4 days:
Work done = \( 4 \times \left( \frac{1}{10} + \frac{1}{20} \right) = 4 \times \frac{3}{20} = \frac{3}{5} \)
Remaining work: \( 1 - \frac{3}{5} = \frac{2}{5} \)
Step 2: A and C do remaining work in 2 days:
\( 2 \times \left( \frac{1}{10} + \frac{1}{C} \right) = \frac{2}{5} \)
Dividing both sides by 2:
\( \frac{1}{10} + \frac{1}{C} = \frac{1}{5} \)
\( \frac{1}{C} = \frac{1}{5} - \frac{1}{10} = \frac{1}{10} \)
\( \Rightarrow C = 10 \)
Step 1: Rajdhani crosses a platform equal to its length in 36 sec.
Let length of Rajdhani = L meters ⇒ Platform = L meters ⇒ Total distance = 2L meters
Speed = 54 km/hr = 15 m/s
So, 2L = 15 × 36 = 540 ⇒ L = 270 m
Step 2: Duronto (length 230 m) crosses same platform (270 m) = total distance = 500 m
Time = 25 sec
Speed = Distance / Time = 500 / 25 = 20 m/s
Convert to km/hr: 20 × 18 / 5 = 72 km/hr