Which of the following are the primary objectives of risk monitoring in software project tracking?
$P$: To assess whether predicted risks do, in fact, occur
$Q$: To ensure that risk aversion steps defined for the risk are being properly applied
$R$: To collect information that can be used for future risk analysis
Risk monitoring is used to track risks during a software project.
It checks whether predicted risks actually occur.
It also checks whether risk avoidance or risk reduction steps are being applied properly.
It also collects risk-related information so that it can be used in future risk analysis.
Therefore, all $P,Q,R$ are correct.
Software validation mainly checks for inconsistencies between:
Software validation checks whether the software specification actually satisfies the user's real requirements.
It answers the question:
Are we building the right product?
So, validation mainly checks inconsistencies between detailed specifications and user requirements.
| List-I (Testing Type) | List-II (Description) |
| A. Unit testing | I. Testing individual components of the software |
| B. Integration testing | II. Testing the interaction between integrated components |
| C. System testing | III. Testing to verify the system meets business needs |
| D. Acceptance testing | IV. Testing the complete system to ensure it meets requirements |
Choose the correct answer from the options given below.
Unit Testing → Testing individual components
Integration Testing → Testing interaction between modules
System Testing → Testing the complete system
Acceptance Testing → Verifying business/user requirements
Thus mapping:
A → I
B → II
C → IV
D → III
Which of the following is not one of the principles of good coding?
In a system for a restaurant, the main scenario for placing an order is given below:
(a) Customer reads menu
(b) Customer places order
(c) Order is sent to the kitchen for preparation
(d) Ordered items are served
(e) Customer requests for a bill for the order
(f) Bill is prepared for this order
(g) Customer is given the bill
(h) Customer pays the bill
A sequence diagram for the scenario will have at least how many objects among whom the messages will be exchanged.
In this restaurant ordering system, the minimum important objects are:
Customer
Menu
Order
Kitchen
Bill
Messages are exchanged among these objects during order placement, food preparation, serving, bill generation and payment.
So, at least $5$ objects are required in the sequence diagram.