Question Id : 17518 |
Context : UGC NET Computer Science August 2024 (Paper II)
Given a project that uses the COCOMO model with an estimated effort of 2000 person-months and a productivity rate of 5 person-month per KLOC, what is the estimated size of the project in KLOC ?
🎥 Video solution / Text Solution of this question is given below:
Productivity relation:
$Productivity = \dfrac{Effort}{Size}$
Given:
$Effort = 2000$ person-month
$Productivity = 5$ person-month per KLOC